Project Status
WinterbourneWind lodged a Submissions Report and an Amendment Report with the Department of Planning, Housing and Infrastructure (DPHI) in September 2024. The Submissions Report provides responses to public and agency submissions received during the EIS exhibition period. The Submissions Report was prepared in accordance with the State Significant Development Guidelines – Preparing a Submissions Report.
The Amendment Report was on public exhibition from 8 October to 4 November 2024. The exhibition period provided an opportunity for community and stakeholders to review the amended project proposal and make a submission. The feedback to the Amendment Report was overwhelmingly positive, with 70% of public submissions indicating support for the proposed project.
A second Submissions Report has now been lodged which provides responses to issues raised by stakeholders and community during exhibition of the Amendment Report. DPHI will now complete its evaluation of the proposed Project and prepare an assessment report, taking into consideration the EIS, Amendment Report and Submissions Reports. DPHI will then make a recommendation to the Minister for Planning and Public Places, who is expected to refer the project to the Independent Planning Commission (IPC). We expect a determination by late 2025 or early 2026.
Project Timeline
2009
Site Identification
Early project development and wind monitoring.
2019
Project Acquisition
Wind Power Invest A/S, a wholly-owned subsidiary of global wind energy company Vestas, acquires a 95% project stake in WinterbourneWind Pty Ltd
September 2020
Submit Scoping Report
A Scoping Report for the project was submitted to NSW Department of Planning and Environment (DPE). The report incorporates results from preliminary environmental assessments and community engagement work.
September 2020
SEARs Issued
The Secretary’s Environmental Assessment Requirements (SEARs) for this project were issued by DPE, following consultation with local Councils and government agencies.
Late 2020
Establish CCC
A Community Consultative Committee (CCC) was established for the project. The CCC consists of an independent Chair, community members, local government representatives and project team members.
Late 2022
Environmental Assessment
The Environmental Impact Statement (EIS) for the project was submitted to DPE in November 2022. The EIS assessed the visual, noise, ecological and other potential environmental impacts of the project. The EIS was on public exhibition from mid-November 2022 until late January 2023.
September 2024
Submissions Report and Amendment Report
A Submissions Report and Amendment Report were lodged with DPHI in September 2024. The Submissions Report provided responses to comments made by the public including government agencies on the Environmental Impact Statement (EIS) for the Project. The Amendment Report documented changes to the proposed Project which have been made to address issues raised in submissions and the outcomes of ongoing engagement with the community, landholders, local council and government agencies as well as to improve project outcomes.
June 2025
Submissions Report No. 2
A second submissions report was lodged with DPHI which provides written responses to issues raised in submissions by government agencies and the community during public exhibition of the Amendment Report.
2026
Development Approval
Development consent expected.
2026
Grid Connection
Offer to Connect expected.
2027
Begin Construction
Estimated start of construction.